SCHEDULING THE PRODUCTION OF PREFABRICATION CONSTRUCTION SUPPLY CHAINS CONSIDERING VARIABLE DELIVERY TIMES
- Title
- SCHEDULING THE PRODUCTION OF PREFABRICATION CONSTRUCTION SUPPLY CHAINS CONSIDERING VARIABLE DELIVERY TIMES
- Authors
- Ho, Chung; Zabinsky, Zelda B.; Kim, Yong-Woo
- Ewha Authors
- 김용우
- SCOPUS Author ID
- 김용우

- Issue Date
- 2026
- Journal Title
- JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT
- ISSN
- 1392-3730
1822-3605
- Citation
- JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT vol. 32, no. 3, pp. 415 - 432
- Keywords
- supply chain; scheduling; prefabrication; modularization; construction; optimization; uncertainty; stochastic programming.
- Publisher
- VILNIUS GEDIMINAS TECH UNIV
- Indexed
- SCIE; SCOPUS

- Document Type
- Article
- Abstract
- cently. The efficiency of prefabrication supply chains yields substantial advantages for construction projects. A challenge is the variability in delivery times, which negatively impacts the economy and reliability of prefabrication supply chains. Most construction prefabrication suppliers have difficulty adjusting their schedules in response to delivery time changes in a timely manner. Despite this critical challenge, limited research has addressed proactive and robust production scheduling to mitigate these uncertainties. This study investigates a method for proactive and robust production scheduling for construction prefabrication suppliers, particularly those with multiple fabrication shops, responding to changes in delivery times. This paper introduces a multi-objective, two-stage stochastic programming model that facilitates the production planning with multiple fabrication shops, considering variable delivery times. Computational results from an experimental study demonstrate that the proposed optimization model achieves a 14.6% cost reduction compared to the traditional EDD method. Computational results also show that the expected cost of the stochastic programming model achieves a cost reduction of 0.23% compared to a deterministic model. These findings suggest the model's capability to generate robust and flexible schedules that effectively balance cost minimization with time reduction.
- DOI
- 10.3846/jcem.2026.26156
- Appears in Collections:
- 공과대학 > 건축도시시스템공학과 > Journal papers
- Files in This Item:
-
26156.pdf(2.26 MB)
Download
- Export
- RIS (EndNote)
- XLS (Excel)
- XML